St. Croix bridge won't open until late 2017

Go Deeper.
Create an account or log in to save stories.
Like this?
Thanks for liking this story! We have added it to a list of your favorite stories.
The St. Croix Crossing project connecting Minnesota and Wisconsin near Stillwater won't open until the fall of 2017.
Minnesota Department of Transportation spokesperson Kevin Gutknecht said setbacks have pushed back the open date; it was originally slated to open in November 2016.
He cited weather, worker shortages, equipment breakdowns, material shortages and complications in the design for slowing down the timeline.
Gutknecht said the Transportation Department is negotiating with Lunda/Ames Joint Venture, the contractor, on a changed contract for the later open date.