More than two years after Rapidan Dam failure, FEMA provides $21M for its removal

Water flows in a river
Water in the Blue Earth River flows around the the Rapidan Dam southwest of Mankato, Minn., Monday June 24, 2024 threatening the integrity of the dam as well as a house on the west side of the dam.
Ken Klotzbach for MPR News

Quick Read

More than $21 million in federal funding was approved to help remove the Rapidan Dam in southern Minnesota and to restore both banks of the Blue Earth River. It'll also help construct a new parking area with easier river access for recreational use.

More than two years after the Rapidan Dam partially collapsed and the Blue Earth River’s floodwaters ravaged the riverbanks around it, federal officials have approved more than $21 million to tear down the 116-year-old structure and to restore the surrounding area.

Heavy rainfall over several days caused severe flooding in late June of 2024, and the Rapidan Dam, which is about 14 miles southwest of Mankato, failed and was overtopped. Dramatic images and video of the dam's failure went viral, as the rain-swollen Blue Earth River carved a path around the dam through a sandstone bluff, and sent a house falling into the raging water.

A view of the Blue Earth River after it cleared by the Rapidan Dam.
This long-exposure drone photo provided by AW Aerial shows a home as it teeters before partially collapsing into the Blue Earth River at the Rapidan Dam in Rapidan, Minn., Tuesday, June 25, 2024.
Andrew Weinzierl | AW Aerial via AP

There was devastation in its wake: It was the Hruska family’s home that toppled into the water. To prevent the same thing from happening to their restaurant, the Rapidan Dam Store, Blue Earth County bought it and demolished it to protect properties downstream.

The dam’s failure also churned up more than a century’s worth of sediment and pollutants from the river bottom, including phosphorus and nitrogen from agricultural runoff, and flushed it downstream.

Rapidan Dam is seen
The waters of the Blue Earth River head downstream at a tremendous speed on Monday evening, southwest of Mankato, Minn., Monday June 24, 2024.. Even if the Rapidan Dam has a complete failure, officials say that the river level in Mankato will only rise two feet.
Jackson Forderer for MPR News

The Federal Emergency Management Agency approved the federal funding to support “locally developed long-term solutions” to remove the dam and restore both banks of the Blue Earth River at the dam site. It’ll also help construct a new parking area alongside the river to provide easier river access for canoes and kayaks.

The $21 million from FEMA is close to covering the “total project cost” of an estimated $28 million, said Ryan Thilges, public works director for Blue Earth County. He said the county anticipates that the state will cover the remaining $7 million. He thanked federal and state agencies, along with county employees, for helping move the project forward.

Two images compare the river damage caused by flooding.
This combination of satellite images provided by MaxarTechnologies shows views of the Rapidan Dam on Minnesota’s Blue Earth River, south of Mankato, on Sept. 6, 2011, top, and bottom on June 26, 2024, after floodwaters overcame parts of the structure following heavy rainfall.
Satellite image ©2024 Maxar Technologies via AP

“It’s really been a big lift, and there’s been a lot of cooperation that’s happened because of it,” Thilges said. “That’s really helped this move along the way it has.”

The complicated process took more than two years, Thilges said, but it meant navigating through “an unknown territory.”

“We build bridges and roads, that’s our bread and butter,” he said. “Taking out a hydroelectric dam like this is much less of a known process. We really had to discover who had authority, who was in charge, and kind of learn what role all of those different agencies played, and that took quite a bit of time.”

County Road 9 Bridge and dam removal projects

Work is already underway to replace the adjacent County Road 9 bridge, which was also severely damaged in the June 2024 flooding. Construction started last month, and officials expect to reopen the bridge in November or December of 2028.

Meanwhile, the planning to remove the Rapidan Dam is currently in its preliminary engineering phase, as officials define its scope and explore design alternatives. Removal is anticipated to start in spring or summer 2027, and depending on the river flows, could take up to two years.

The ruins of a dam
The ruins of the Rapidan Dam remain along the Blue Earth River months after a flood compromised the dam and the Highway 9 bridge in the background. Blue Earth County commissioners have already voted to demolish the dam. Today Governor Tim Walz announced a proposed bill that would fund repair of the highway bridge. Photographed on Oct. 27, 2024.
Jackson Forderer for MPR News

Thilges said the county is closely monitoring the logistics of coordinating the two ongoing construction and demolition projects in such a cramped space.

“There’s certainly going to be some complexities associated with that,” Thilges said, “and just because of the geographical constraints at the site, getting in and out of there and having access to the river… Real estate’s at a premium, especially in that valley.”

Moving forward

Thilges said that more than two years after the Rapidan Dam failure, he and other public works officials have learned a lot about severe weather and its potentially catastrophic impacts on public infrastructure. And he is looking at folding those lessons into plans for preventing something like this from happening again, especially amid a changing climate.

“We’ve got aging infrastructure, but we’re also facing more severe and more frequent events that are leading to more significant damages,” Thilges said. “So, we really need to put an emphasis on adequate funding and programs to ensure that our infrastructure, whether it’s dams, roads, bridges to really bolster the resiliency of our infrastructure.”

A construction worker moves concrete
A construction worker looks at a large chunk of concrete and rebar that was taken off of the Highway 9 bridge moments earlier at the site of the Rapidan Dam in Mankato, Minn., on Thursday, Jan. 23, 2025.